Skip to main content

What is the startup and shutdown procedure of an interpreter lab?

Learn the correct order to start up and shut down the equipment of an interpreter lab.

How to start up the system?

1. Start the rack with the following equipment:

  • Plixus AE-R

  • Control PC

  • Lingua-T

  • Dante / Lan switches

Note: Make sure that everything is switched on before you start the teacher PC.

2. Start the teacher PC and interpreterQ.

3. Start the computers in booth 01-02-…

How to shut down the system?

1. Switch off the computers in booth 01-02-…

2. Switch off the teacher PC.

3. Switch off the Control PC in the rack (ERS service running on that computer).

4. Switch off the rack.